Sewerage Backlog Areas

South East Water Limited has liaised with the Environment Protection Authority (EPA) and those Councils within its area with unsewered properties that are considered as meeting the criteria for inclusion in the program, to clearly define the extent of the future program.

 

The process also revisited the criteria for setting the priority order for construction works and has scheduled the projects on the basis of the current government budget spend requirement.

Councils involved were Mornington Peninsula, Casey, Cardinia, Yarra Ranges, Knox and Frankston.

 

The total number of unsewered lots included on the program is 23,000 and the total cost in today's dollars of providing sewerage services to all these unsewered lots is estimated at $400 million.

 

The process has been documented in the South East Water publication - Backlog Sewerage Program - Protecting the Environment and your Health. This publication also includes clearly defined plans showing which properties are included on the program and a schedule of when they are likely to be sewered.

 

All defined area plans have been endorsed by the respective Council Chief Executive Officers. The program is regularly reviewed and adjustments can result from;

  • Changes in Government direction on annual spending on the program;
  • Altered priorities as a result of changes in the environmental or health conditions in an area;
  • Changes in project costs.

 Sewerage Backlog Areas (376KB)

 Backlog Sewerage Program - Protecting the Environment and your Health (134KB) 
 

South East Water Priority Backlog Sewerage Program as at December 2004

(Indicative only and subject to annual review)

Township Municipality Number of Lots Indic've Start date Indic've Finish date Remarks
Rye coastal Stage 2 Morn. Pen. 348 2004/05 2004/05 Under construction
Flinders Morn. Pen. 795 2005/06 2007/08 Design Commenced - Transfer pipeline to Somers Sewerage Treatment Plant
Shoreham Morn. Pen. 431 2007/08 2008/09 Common treatment/transfer system with Flinders
Olivers Hill, Frankston Frankston 8 2004/05 2004/05 Unstable land - sewerage to be "pumped up" to gravity main
Churchill Park Drive Casey 33 2005/06 2005/06 Impacts on new adjacent development, design & construct in conjunction with drain
Nar Nar Goon Cardinia 170 2008/09 2008/09 Transfer pipeline to Pakenham Sewerage Treatment Plant or new local treatment plant (combined system with Tynong)
Tynong Cardinia 131 2009/10 2009/10 Combined transfer / treatment systems with Nar Nar Goon
Rye Coastal Stage 3 Morn. Pen. 429 2008/09 2009/10 Connects to existing Rye Commercial - design commenced
Sherbrooke Area B Yarra Ranges 582 2010/11 2011/12 Connects to existing systems
Upper Beaconsfield Cardinia 220 2011/12 2011/12 New transfer system to Adamsons Rd required
Sherbrooke Area A Yarra Ranges 145 2011/12 2011/12 Connects to existing systems
Sherbrooke Area C Yarra Ranges 822 2011/12 2013/14 Connects to existing systems
Narre Warren North Casey 108 2012/13 2012/13 New PS and outfall required, to be provided by new development over next 2 years
Rye Coastal Stage 4 Morn. Pen. 423 2013/14 2014/15 Connects to existing Rye Commercial
Rye Coastal Stage 5 Morn. Pen. 435 2014/15 2015/16 Connects to existing Rye Commercial
Rye Coastal Stage 6 Morn. Pen. 470 2015/16 2016/17 Connects to existing Rye Commercial
Rye Area A Morn. Pen. 2210 2016/17 2019/20 New South Peninsula transfer system to Boneo Sewerage Treatment Plant
Blairgowrie Area A Morn. Pen. 2690 2019/20 2024/25 Outfalls to Rye A - extension of South Peninsula transfer system
Sorrento Area A Morn. Pen. 1700 2024/25 2027/28 Connects to Blairgowrie A - extension of South Peninsula transfer system
Sorrento Area B Morn. Pen. 294 2027/28 2027/28 Connects to Sorrento A - extension of South Peninsula transfer system
Portsea Morn. Pen. 1420 2027/28 2031/32 Connect to Sorrento B
Pt Leo Morn. Pen. 46 2030/31 2030/31 Connects to Shoreham / Flinders transfer system
Rye Area B Morn. Pen. 2000 2031/32 2033/34 Connects to South Peninsula transfer system
Rye Area C Morn. Pen. 3360 2033/34 2038/39 Connects to South Peninsula transfer system
Blairgowrie Area B Morn. Pen. 1240 2038/39 2040/41 Connects to Blairgowrie A
Sorrento Area C Morn. Pen. 1360 2040/41 2042/43 Connects to Sorrento A
St Andrews Beach Morn. Pen. 766 2042/43 2043/44 New transfer system to Boneo Sewerage Treatment Plant
Clyde Casey 56 2043/44 2043/44 Very remote - New transfer system or local treatment plant required
Officer Cardinia 105 2043/44 2043/44 New pump station and and transfer system required
Cape Schank Morn. Pen. 188 2043/44 2043/44 Management of existing STP and retic extension to abutting non-sewered areas
Milleara Rd, The Basin Knox 30 2043/44 2043/44 Connect to existing system
Total 23015

 

Defined Area Plans
 
Below are the individual plans defining the extent of each backlog area.
 
 Blairgowrie Area A Plan   (834KB) 
 Blairgowrie Area B Plan   (755KB) 
 Cape Schanck Area Plan   (247KB) 
 Churchill Park Area Plan   (142KB) 
 Clyde Area Plan   (66KB) 
 Flinders Area Plan   (285KB) 
 Milleara Rd The Basin Area Plan   (85KB) 
 Nar Nar Goon Area Plan   (71KB) 
 Narre Warren North Area Plan   (203KB) 
 Officer Area Plan   (124KB) 
 Olivers Hill, Frankston Area Plan   (120KB) 
 Point Leo Area Plan   (91KB) 
 Portsea Area Plan   (539KB) 
 Rye Area A Plan   (472KB) 
 Rye Area B Plan   (598KB) 
 Rye Area C Plan   (691KB) 
 Rye Coastal Stages 1 to 6 Plan   (786KB) 
 Sherbrooke Area A Plan   (352KB) 
 Sherbrooke Area B Plan   (458KB) 
 Sherbrooke Area C Plan   (345KB) 
 Shoreham Area Plan   (239KB) 
 Sorrento Area A Plan   (519KB) 

 Sorrento Area B Plan   (264KB) 
 Sorrento Area C Plan   (648KB) 
 St Andrews Beach Area Plan   (335KB) 
 Tynong Area Plan   (59KB) 
 Upper Beaconsfield Area Plan   (194KB) 
 

Home | Terms | Privacy | Complaints | Site Map
Copyright © 2007 South East Water Ltd | ABN 89 066 902 547
20 Corporate Drive Heatherton Victoria 3202 Australia | Ph: 03 9552 3000