South East Water Limited has liaised with the Environment Protection Authority (EPA) and those Councils within its area with unsewered properties that are considered as meeting the criteria for inclusion in the program, to clearly define the extent of the future program.
The process also revisited the criteria for setting the priority order for construction works and has scheduled the projects on the basis of the current government budget spend requirement.
Councils involved were Mornington Peninsula, Casey, Cardinia, Yarra Ranges, Knox and Frankston.
The total number of unsewered lots included on the program is 23,000 and the total cost in today's dollars of providing sewerage services to all these unsewered lots is estimated at $400 million.
The process has been documented in the South East Water publication - Backlog Sewerage Program - Protecting the Environment and your Health. This publication also includes clearly defined plans showing which properties are included on the program and a schedule of when they are likely to be sewered.
All defined area plans have been endorsed by the respective Council Chief Executive Officers. The program is regularly reviewed and adjustments can result from;
- Changes in Government direction on annual spending on the program;
- Altered priorities as a result of changes in the environmental or health conditions in an area;
- Changes in project costs.
Sewerage Backlog Areas (376KB)
Backlog Sewerage Program - Protecting the Environment and your Health (134KB)
|
South East Water Priority Backlog Sewerage Program as at December 2004 |
|
(Indicative only and subject to annual review) |
 |
 |
 |
 |
 |
 |
| Township |
Municipality |
Number of Lots |
Indic've Start date |
Indic've Finish date |
Remarks |
| Rye coastal Stage 2 |
Morn. Pen. |
348 |
2004/05 |
2004/05 |
Under construction |
| Flinders |
Morn. Pen. |
795 |
2005/06 |
2007/08 |
Design Commenced - Transfer pipeline to Somers Sewerage Treatment Plant |
| Shoreham |
Morn. Pen. |
431 |
2007/08 |
2008/09 |
Common treatment/transfer system with Flinders |
| Olivers Hill, Frankston |
Frankston |
8 |
2004/05 |
2004/05 |
Unstable land - sewerage to be "pumped up" to gravity main |
| Churchill Park Drive |
Casey |
33 |
2005/06 |
2005/06 |
Impacts on new adjacent development, design & construct in conjunction with drain |
| Nar Nar Goon |
Cardinia |
170 |
2008/09 |
2008/09 |
Transfer pipeline to Pakenham Sewerage Treatment Plant or new local treatment plant (combined system with Tynong) |
| Tynong |
Cardinia |
131 |
2009/10 |
2009/10 |
Combined transfer / treatment systems with Nar Nar Goon |
| Rye Coastal Stage 3 |
Morn. Pen. |
429 |
2008/09 |
2009/10 |
Connects to existing Rye Commercial - design commenced |
| Sherbrooke Area B |
Yarra Ranges |
582 |
2010/11 |
2011/12 |
Connects to existing systems |
| Upper Beaconsfield |
Cardinia |
220 |
2011/12 |
2011/12 |
New transfer system to Adamsons Rd required |
| Sherbrooke Area A |
Yarra Ranges |
145 |
2011/12 |
2011/12 |
Connects to existing systems |
| Sherbrooke Area C |
Yarra Ranges |
822 |
2011/12 |
2013/14 |
Connects to existing systems |
| Narre Warren North |
Casey |
108 |
2012/13 |
2012/13 |
New PS and outfall required, to be provided by new development over next 2 years |
| Rye Coastal Stage 4 |
Morn. Pen. |
423 |
2013/14 |
2014/15 |
Connects to existing Rye Commercial |
| Rye Coastal Stage 5 |
Morn. Pen. |
435 |
2014/15 |
2015/16 |
Connects to existing Rye Commercial |
| Rye Coastal Stage 6 |
Morn. Pen. |
470 |
2015/16 |
2016/17 |
Connects to existing Rye Commercial |
| Rye Area A |
Morn. Pen. |
2210 |
2016/17 |
2019/20 |
New South Peninsula transfer system to Boneo Sewerage Treatment Plant |
| Blairgowrie Area A |
Morn. Pen. |
2690 |
2019/20 |
2024/25 |
Outfalls to Rye A - extension of South Peninsula transfer system |
| Sorrento Area A |
Morn. Pen. |
1700 |
2024/25 |
2027/28 |
Connects to Blairgowrie A - extension of South Peninsula transfer system |
| Sorrento Area B |
Morn. Pen. |
294 |
2027/28 |
2027/28 |
Connects to Sorrento A - extension of South Peninsula transfer system |
| Portsea |
Morn. Pen. |
1420 |
2027/28 |
2031/32 |
Connect to Sorrento B |
| Pt Leo |
Morn. Pen. |
46 |
2030/31 |
2030/31 |
Connects to Shoreham / Flinders transfer system |
| Rye Area B |
Morn. Pen. |
2000 |
2031/32 |
2033/34 |
Connects to South Peninsula transfer system |
| Rye Area C |
Morn. Pen. |
3360 |
2033/34 |
2038/39 |
Connects to South Peninsula transfer system |
| Blairgowrie Area B |
Morn. Pen. |
1240 |
2038/39 |
2040/41 |
Connects to Blairgowrie A |
| Sorrento Area C |
Morn. Pen. |
1360 |
2040/41 |
2042/43 |
Connects to Sorrento A |
| St Andrews Beach |
Morn. Pen. |
766 |
2042/43 |
2043/44 |
New transfer system to Boneo Sewerage Treatment Plant |
| Clyde |
Casey |
56 |
2043/44 |
2043/44 |
Very remote - New transfer system or local treatment plant required |
| Officer |
Cardinia |
105 |
2043/44 |
2043/44 |
New pump station and and transfer system required |
| Cape Schank |
Morn. Pen. |
188 |
2043/44 |
2043/44 |
Management of existing STP and retic extension to abutting non-sewered areas |
| Milleara Rd, The Basin |
Knox |
30 |
2043/44 |
2043/44 |
Connect to existing system |
| Total |
|
23015 |
|
| |
Defined Area Plans
Below are the individual plans defining the extent of each backlog area.
Blairgowrie Area A Plan (834KB)
Blairgowrie Area B Plan (755KB)
Cape Schanck Area Plan (247KB)
Churchill Park Area Plan (142KB)
Clyde Area Plan (66KB)
Flinders Area Plan (285KB)
Milleara Rd The Basin Area Plan (85KB)
Nar Nar Goon Area Plan (71KB)
Narre Warren North Area Plan (203KB)
Officer Area Plan (124KB)
Olivers Hill, Frankston Area Plan (120KB)
Point Leo Area Plan (91KB)
Portsea Area Plan (539KB)
Rye Area A Plan (472KB)
Rye Area B Plan (598KB)
Rye Area C Plan (691KB)
Rye Coastal Stages 1 to 6 Plan (786KB)
Sherbrooke Area A Plan (352KB)
Sherbrooke Area B Plan (458KB)
Sherbrooke Area C Plan (345KB)
Shoreham Area Plan (239KB)
Sorrento Area A Plan (519KB)
Sorrento Area B Plan (264KB)
Sorrento Area C Plan (648KB)
St Andrews Beach Area Plan (335KB)
Tynong Area Plan (59KB)
Upper Beaconsfield Area Plan (194KB)